PROPOSED PROJECT
- Construct a replacement 10,113-foot runway, parallel to and at a minimum of 702 feet south of existing Runway 10R/28L
- Construct parallel taxiways to support the relocation of Runway 10R/28L
- Construct a new passenger terminal and apron in the midfield area
- Stormwater Detention Basin
- Relocate Airport Perimeter Road
- Site selection, purchase, installation, and flight checks of all necessary NAVAIDs and lighting to support the proposed development
- Implementation of necessary air traffic control procedures to support the proposed development
- Implementation of ancillary facilities to support the proposed development
- Acquisition and demolition of 36 parcels (35 homes) located on Thirteenth Avenue in the City of Columbus
- Reconfiguration of Airport Golf Course to accommodate new landing lights on the east side of the Airport
- Relocation of a portion of Stelzer Road to the west to accommodate landing light locations
- Removal of the non-functioning control tower from the top of Building 7 of the International Aircenter

Existing Airport Layout

Sponsors Proposed Project
|